XV. EMERGENCY RESPONSE

52. In the event of any action or occurrence during the performance of the Work which causes or threatens a release of Waste Material from the Site that constitutes an emergency situation or may present an immediate threat to public health or welfare or the environment, Settling Defendants shall, subject to Paragraph 53, immediately take all appropriate action to prevent, abate, or minimize such release or threat of release, and shall immediately notify, the EPA's Project Coordinator, or, if the Project Coordinator is unavailable, EPA's Alternate Project Coordinator. If neither of these persons is available, the Settling Defendants shall notify, during business hours, the Chief, Response & Prevention Branch, Region 2 at (732) 321-6656. Settling Defendants shall also immediately notify the NJDEP Emergency Hotline, (609) 292-7172. Settling Defendants shall take such actions in consultation with EPA's Project Coordinator or other available authorized EPA officer and in accordance with all applicable provisions of the Health and Safety Contingency Plans, and any other applicable plans or documents developed pursuant to the SOW. In the event that Settling Defendants fail to take appropriate response action as required by this Section, and EPA, as appropriate, takes such action instead, Settling Defendants shall reimburse EPA all costs of the response action not inconsistent with the NCP pursuant to Section XVI (Payment for Response Costs).

53. Nothing in the preceding Paragraph or in this Consent Decree shall be deemed to limit any authority of the United States: a) to take all appropriate action to protect human health and the environment or to prevent, abate, respond to, or minimize an actual or threatened release of Waste Material on, at, or from the Site, or b) to direct or order such action, or seek an order from the Court, to protect human health and the environment or to prevent, abate, respond to, or minimize an actual or threatened release of Waste Material on, at, or from the Site, subject to Section XXI (Covenants Not to Sue by Plaintiffs).

XVI. PAYMENTS FOR RESPONSE COSTS


54. Payments for Past Response Costs.

a. Within 30 days of the Effective Date, Settling Defendants shall pay to EPA $250,000 in full satisfaction of Past Response Costs. Payment shall be made by FedWire Electronic Funds Transfer ("EFT") to the U.S. Department of Justice account in accordance with current EFT procedures, referencing USAO File Number ____, EPA Site/Spill ID Number 0287, and DOJ Case Number 90-11-2-289/1. Payment shall be made in accordance with instructions provided to the Settling Defendants by the Financial Litigation Unit of the United States Attorney's Office for the District of New Jersey following lodging of the Consent Decree. Any payments received by the Department of Justice after 4:00 p.m. (Eastern Time) will be credited on the next business day.

b. At the time of payment, Settling Defendants shall send notice that payment has been made to the United States, to EPA and to the Regional Financial Management Officer, in accordance with Section XXVI (Notices and Submissions). The total amount to be paid by Settling Defendants pursuant to subparagraph "a" shall be deposited in the EPA Hazardous Substance Superfund.

55. Payments for Future Response Costs.

Settling Defendants shall pay to EPA all Future Response Costs not inconsistent with the National Contingency Plan. On a periodic basis the United States will send Settling Defendants a bill requiring payment that includes a SCORPIOS printout of cost data from EPA's financial management system, and, if appropriate, a summary of costs incurred by the United States Department of Justice. The Settling Defendants shall make all payments required by this Paragraph by FedWire EFT. To effect the payment via EFT, Settling Defendant shall provide the following information to its bank:

i. Amount of Payment:

ii. Title of Mellon Bank Account to receive the payment: EPA

iii. Account code for Mellon Bank receiving the payment: 9108544

iv. Mellon Bank ABA Routing Number: 043000261

v. Name of remitter:

vi. Case number:

vii. Site/Spill Identifier: 02-87

Along with this information, Settling Defendant shall instruct its bank to remit payment in the agreed amount via EFT to EPA's account with Mellon Bank.

To ensure that payment is properly recorded, Settling Defendant shall send a letter, within one week of the EFT, which references the date of the EFT, the payment amount, the name of the site, the case number, and your name and address to the United States, to EPA and to the Regional Financial Management Officer, in accordance with Section XXVI (Notices and Submissions).

56. Settling Defendants may contest payment of any Future Response Costs under Paragraph 55 if they determine that the United States has made an accounting error or if they allege that a cost item that is included represents costs that are inconsistent with the NCP. Such objection shall be made in writing within 30 days of receipt of the bill and must be sent to the United States (if the United States' accounting is being disputed) pursuant to Section XXVI (Notices and Submissions). Any such objection shall specifically identify the contested Future Response Costs and the basis for objection. In the event of an objection, the Settling Defendants shall within the 30 day period pay all uncontested Future Response Costs to the United States in the manner described in Paragraph 55. Simultaneously, the Settling Defendants shall establish an interest-bearing escrow account in a federally-insured bank doing business in the State of New Jersey and remit to that escrow account funds equivalent to the amount of the contested Future Response Costs. The Settling Defendants shall send to the United States, as provided in Section XXVI (Notices and Submissions), a copy of the transmittal letter and check paying the uncontested Future Response Costs, and a copy of the correspondence that establishes and funds the escrow account, including, but not limited to, information containing the identity of the bank and bank account under which the escrow account is established as well as a bank statement showing the initial balance of the escrow account. Simultaneously with establishment of the escrow account, the Settling Defendants shall initiate the Dispute Resolution procedures in Section XIX (Dispute Resolution). If the United States prevails in the dispute, within 5 days of the resolution of the dispute, the Settling Defendants shall pay the sums due (with accrued interest) to the United States, in the manner described in Paragraph 55. If the Settling Defendants prevail concerning any aspect of the contested costs, the Settling Defendants shall pay that portion of the costs (plus associated accrued interest) for which they did not prevail to the United States in the manner described in Paragraph 55; Settling Defendants shall be disbursed any balance of the escrow account. The dispute resolution procedures set forth in this Paragraph in conjunction with the procedures set forth in Section XIX (Dispute Resolution) shall be the exclusive mechanisms for resolving disputes regarding the Settling Defendants' obligation to reimburse the United States for its Future Response Costs.

57. In the event that the payments required by Paragraph 55 are not made within 30 days of the Settling Defendants' receipt of the bill, Settling Defendants shall pay Interest on the unpaid balance. The Interest to be paid on Past Response Costs under this Paragraph shall begin to accrue 30 days after the Effective Date. The Interest on Future Response Costs shall begin to accrue on the date of the bill. The Interest shall accrue through the date of the Settling Defendant's payment. Payments of Interest made under this Paragraph shall be in addition to such other remedies or sanctions available to Plaintiffs by virtue of Settling Defendants' failure to make timely payments under this Section. The Settling Defendants shall make all payments required by this Paragraph in the manner described in Paragraph 55.

XVII. INDEMNIFICATION AND INSURANCE


58. Settling Defendant's Indemnification of the United States.

A. The United States does not assume any liability by entering into this agreement or by virtue of any designation of Settling Defendants as EPA's authorized representatives under Section 104(e) of CERCLA. Settling Defendants shall indemnify, save and hold harmless the United States, and their officials, agents, employees, contractors, subcontractors, or representatives for or from any and all claims or causes of action arising from, or on account of, negligent or other wrongful acts or omissions of Settling Defendants, their officers, directors, employees, agents, contractors, subcontractors, and any persons acting on their behalf or under their control, in carrying out activities pursuant to this Consent Decree, including, but not limited to, any claims arising from any designation of Settling Defendants as EPA's authorized representatives under Section 104(e) of CERCLA. Further, the Settling Defendants agree to pay the United States all costs they incur including, but not limited to, attorneys fees and other expenses of litigation and settlement arising from, or on account of, claims made against the United States based on negligent or other wrongful acts or omissions of Settling Defendants, their officers, directors, employees, agents, contractors, subcontractors, and any persons acting on their behalf or under their control, in carrying out activities pursuant to this Consent Decree. The United States shall not be held out as a party to any contract entered into by or on behalf of Settling Defendants in carrying out activities pursuant to this Consent Decree. Neither the Settling Defendants nor any such contractor shall be considered an agent of the United States.

B. The United States shall give Settling Defendants notice of any claim for which the United States plans to seek indemnification pursuant to Paragraph 58, and shall consult with Settling Defendants prior to settling such claim.

59. Settling Defendants waive all claims against the United States for damages or reimbursement or for set-off of any payments made or to be made to the United States, arising from or on account of any contract, agreement, or arrangement between any one or more of Settling Defendants and any person for performance of Work on or relating to the Site, including, but not limited to, claims on account of construction delays. In addition, Settling Defendants shall indemnify and hold harmless the United States with respect to any and all claims for damages or reimbursement arising from or on account of any contract, agreement, or arrangement between any one or more of Settling Defendants and any person for performance of Work on or relating to the Site, including, but not limited to, claims on account of construction delays.

60. No later than 15 days before commencing any on-site Work, Settling Defendants shall secure, and shall maintain until the first anniversary of EPA's Certification of Completion of the Remedial Action pursuant to Subparagraph 50.b of Section XIV (Certification of Completion) comprehensive general liability insurance with limits of $3 million dollars, combined single limit, and automobile liability insurance with limits of $1 million dollars, combined single limit, naming the United States as an additional insured. In addition, for the duration of this Consent Decree, Settling Defendants shall satisfy, or shall ensure that their contractors or subcontractors satisfy, all applicable laws and regulations regarding the provision of worker's compensation insurance for all persons performing the Work on behalf of Settling Defendants in furtherance of this Consent Decree. Prior to commencement of the Work under this Consent Decree, Settling Defendants shall provide to EPA certificates of such insurance and a copy of each insurance policy. Settling Defendants shall resubmit such certificates and copies of policies each year on the anniversary of the Effective Date. If Settling Defendants demonstrate by evidence satisfactory to EPA that any contractor or subcontractor maintains insurance equivalent to that described above, or insurance covering the same risks but in a lesser amount, then, with respect to that contractor or subcontractor, Settling Defendants need provide only that portion of the insurance described above which is not maintained by the contractor or subcontractor.

XVIII. FORCE MAJEURE


61. "Force majeure," for purposes of this Consent Decree, is defined as any event arising from causes beyond the control of the Settling Defendants, of any entity controlled by Settling Defendants, or of Settling Defendants' contractors, that delays or prevents the performance of any obligation under this Consent Decree despite Settling Defendants' best efforts to fulfill the obligation. The requirement that the Settling Defendants exercise "best efforts to fulfill the obligation" includes using best efforts to anticipate any potential force majeure event and best efforts to address the effects of any potential force majeure event (1) as it is occurring and (2) following the potential force majeure event, such that the delay is minimized to the greatest extent possible. "Force Majeure" does not include financial inability to complete the Work or a failure to attain the Performance Standards.

62. If any event occurs or has occurred that may delay the performance of any obligation under this Consent Decree, whether or not caused by a force majeure event, the Settling Defendants shall notify orally EPA's Project Coordinator or, in his or her absence, EPA's Alternate Project Coordinator or, in the event both of EPA's designated representatives are unavailable, the Special Projects Branch Chief, EPA Region II, within four days of when Settling Defendants first knew that the event might cause a delay. Within five days thereafter, Settling Defendants shall provide in writing to EPA an explanation and description of the reasons for the delay; the anticipated duration of the delay; all actions taken or to be taken to prevent or minimize the delay; a schedule for implementation of any measures to be taken to prevent or mitigate the delay or the effect of the delay; the Settling Defendants' rationale for attributing such delay to a force majeure event if they intend to assert such a claim; and a statement as to whether, in the opinion of the Settling Defendants, such event may cause or contribute to an endangerment to public health, welfare or the environment. The Settling Defendants shall include with any notice all available documentation supporting their claim that the delay was attributable to a force majeure. Failure to comply with the above requirements shall preclude Settling Defendants from asserting any claim of force majeure for that event for the period of time of such failure to comply, and for any additional delay caused by such failure. Settling Defendants shall be deemed to know of any circumstance of which Settling Defendants, any entity controlled by Settling Defendants, or Settling Defendants' contractors knew or should have known.

63. If EPA agrees that the delay or anticipated delay is attributable to a force majeure event, the time for performance of the obligations under this Consent Decree that are affected by the force majeure event will be extended by EPA for such time as is necessary to complete those obligations. An extension of the time for performance of the obligations affected by the force majeure event shall not, of itself, extend the time for performance of any other obligation. If EPA does not agree that the delay or anticipated delay has been or will be caused by a force majeure event, EPA will notify the Settling Defendants in writing of its decision. If EPA agrees that the delay is attributable to a force majeure event, EPA will notify the Settling Defendants in writing of the length of the extension, if any, for performance of the obligations affected by the force majeure event.

64. If the Settling Defendants elect to invoke the dispute resolution procedures set forth in Section XIX (Dispute Resolution), they shall do so no later than 15 days after receipt of EPA's notice. In any such proceeding, Settling Defendants shall have the burden of demonstrating by a preponderance of the evidence that the delay or anticipated delay has been or will be caused by a force majeure event, that the duration of the delay or the extension sought was or will be warranted under the circumstances, that best efforts were exercised to avoid and mitigate the effects of the delay, and that Settling Defendants complied with the requirements of Paragraphs 61 and 62, above. If Settling Defendants carry this burden, the delay at issue shall be deemed not to be a violation by Settling Defendants of the affected obligation of this Consent Decree identified to EPA and the Court.

XIX. DISPUTE RESOLUTION


65. Unless otherwise expressly provided for in this Consent Decree, the dispute resolution procedures of this Section shall be the exclusive mechanism to resolve disputes arising under or with respect to this Consent Decree. However, the procedures set forth in this Section shall not apply to actions by the United States to enforce obligations of the Settling Defendants that have not been disputed in accordance with this Section.

66. Any dispute which arises under or with respect to this Consent Decree shall in the first instance be the subject of informal negotiations between the parties to the dispute. The period for informal negotiations shall not exceed 20 days from the time the dispute arises, unless it is modified by written agreement of the parties to the dispute. The dispute shall be considered to have arisen when one party sends the other parties a written Notice of Dispute.

67. Statements of Position.

A. In the event that the parties cannot resolve a dispute by informal negotiations under the preceding Paragraph, then the position advanced by EPA shall be considered binding unless, within 10 days after the conclusion of the informal negotiation period, Settling Defendants invoke the formal dispute resolution procedures of this Section by serving on the United States a written Statement of Position on the matter in dispute, including, but not limited to, any factual data, analysis or opinion supporting that position and any supporting documentation relied upon by the Settling Defendants. The Statement of Position shall specify the Settling Defendants' position as to whether formal dispute resolution should proceed under Paragraph 68 or Paragraph 69.

B. Within 14 days after receipt of Settling Defendants' Statement of Position, EPA will serve on Settling Defendants its Statement of Position, including, but not limited to, any factual data, analysis, or opinion supporting that position and all supporting documentation relied upon by EPA. EPA's Statement of Position shall include a statement as to whether formal dispute resolution should proceed under Paragraph 68 or 69. Within 14 days after receipt of EPA's Statement of Position, Settling Defendants may submit a Reply.

C. If there is disagreement between EPA and the Settling Defendants as to whether dispute resolution should proceed under Paragraph 68 or 69, the parties to the dispute shall follow the procedures set forth in the paragraph determined by EPA to be applicable. However, if the Settling Defendants ultimately appeal to the Court to resolve the dispute, the Court shall determine which paragraph is applicable in accordance with the standards of applicability set forth in Paragraphs 68 and 69.

68. Formal dispute resolution for disputes pertaining to the selection or adequacy of any response action and all other disputes that are accorded review on the administrative record under applicable principles of administrative law shall be conducted pursuant to the procedures set forth in this Paragraph. For purposes of this Paragraph, the adequacy of any response action includes, without limitation: (1) the adequacy or appropriateness of plans, procedures to implement plans, or any other items requiring approval by EPA under this Consent Decree; and (2) the adequacy of the performance of response actions taken pursuant to this Consent Decree. Nothing in this Consent Decree shall be construed to allow any dispute by Settling Defendants regarding the validity of the ROD's provisions.

A. An administrative record of the dispute shall be maintained by EPA and shall contain all statements of position, including supporting documentation, submitted pursuant to this Section. Where appropriate, EPA may allow submission of supplemental statements of position by the parties to the dispute.

B. The Director of the Emergency and Remedial Response Division, EPA Region II, will issue a final administrative decision resolving the dispute based on the administrative record described in Paragraph 68.a. This decision shall be binding upon the Settling Defendants, subject only to the right to seek judicial review pursuant to Paragraph 68.c and d.

C. Any administrative decision made by EPA pursuant to Paragraph 68.b. shall be reviewable by this Court, provided that a motion for judicial review of the decision is filed by the Settling Defendants with the Court and served on all Parties within 10 days of receipt of EPA's decision. The motion shall include a description of the matter in dispute, the efforts made by the parties to resolve it, the relief requested, and the schedule, if any, within which the dispute must be resolved to ensure orderly implementation of this Consent Decree. The United States may file a response to Settling Defendants' motion.

D. In proceedings on any dispute governed by this Paragraph, Settling Defendants shall have the burden of demonstrating that the decision of the Director of the Emergency and Remedial Response Division, EPA Region II, is arbitrary and capricious or otherwise not in accordance with law. Judicial review of EPA's decision shall be on the administrative record compiled pursuant to Paragraph 68.a.

69. Formal dispute resolution for disputes that neither pertain to the selection or adequacy of any response action nor are otherwise accorded review on the administrative record under applicable principles of administrative law, shall be governed by this Paragraph.

A. Following receipt of Settling Defendants' Statement of Position submitted pursuant to Paragraph 67, the Director of the Emergency and Remedial response Division, EPA Region II, will issue a final decision resolving the dispute. The Emergency and Remedial Response Director's decision shall be binding on the Settling Defendants unless, within 10 days of receipt of the decision, the Settling Defendants file with the Court and serve on the parties a motion for judicial review of the decision setting forth the matter in dispute, the efforts made by the Parties to resolve it, the relief requested, and the schedule, if any, within which the dispute must be resolved to ensure orderly implementation of the Consent Decree. The United States may file a response to Settling Defendants' motion.

B. Notwithstanding Paragraph L of Section I (Background) of this Consent Decree, judicial review of any dispute governed by this Paragraph shall be governed by applicable principles of law.

70. The invocation of formal dispute resolution procedures under this Section shall not extend, postpone or affect in any way any obligation of the Settling Defendants under this Consent Decree, not directly in dispute, unless EPA or the Court agrees otherwise. Stipulated penalties with respect to the disputed matter shall continue to accrue but payment shall be stayed pending resolution of the dispute as provided in Paragraph 79. Notwithstanding the stay of payment, stipulated penalties shall accrue from the first day of noncompliance with any applicable provision of this Consent Decree. In the event that the Settling Defendants do not prevail on the disputed issue, stipulated penalties shall be assessed and paid as provided in Section XX (Stipulated Penalties).